ANNEX III: MANUALS, TRAINING DESIGN AND COURSE OUTLINE

This is the html version of the file http://dfidweb.dfid.gov.uk/prismdocs/ARCHIVE/ETHIOPIA/542027P1.DOC.
Google automatically generates html versions of documents as we crawl the web.

 

Project
Application
 
 

To 

The Consortium
of Donors 

For 

Training
Journalists and Civil Society Institutions on the PRSP and how to enhance
the Effectiveness of Civil Society Institutions in the Preparation and
Monitoring of the full Poverty Reduction Strategy Paper for Ethiopia
* 

Ethiopian
Economic Association/Ethiopian Economic Policy Research Institute

 
 

Addis
Ababa, December 8, 2000.  
Table of
Content

1. Contextual
Background
 

2. Project
Justification
 

      2.1
Project Objective
 

      2.1.1.
Long-term objectives:
 

      2.1.2.
Short-term objective
 
 

      2.2.
The promoter of the project
 

      2.3.
Organizational structure and governance
 

      2.4.
Project Location
 

3. Outputs and Programming 

      3.1
Activities to be undertaken by the project
 

4.   
Project Duration and training design
 
 

5. Project Budget 
 

1. Contextual Background 

It is not a
very contentious issue anymore that the various policy reform measures
that have been undertaken over the past two decades in various African
countries have produced at best a mixed result and in many cases have
simply failed to achieve the intended objectives. At the core of these
objectives are the reduction and eventually the elimination of the crippling
poverty that torments a very sizable portion of the population in many
poor countries. The underlying assumption that informed the earlier
reform process largely blamed lack of a stable macroeconomic environment
and ill informed sectoral policies pursued by African governments that
led to inefficient resource allocation and prohibited rapid economic
growth, which are considered central to the fight against poverty. 

While the requirements
of a stable macroeconomic environment and efficient resource allocation
through the market system are still acknowledged, it was also realized
that making these policy reforms work requires substantial internal
and external resources. In particular, the requirements of a stable
macro economy and the fiscal prudence that this requires meant elimination
of a number of expenditure programs that cater for the poor (such as
subsidies for staple food products) potentially aggravating the incidence
of poverty unless otherwise supplemented by other poverty reduction
measures. Furthermore, the sizable resources transferred to developed
countries from developing countries by way of debt service payments
have to be substantially reduced if resources are to be available for
poverty reduction programs on the one hand and to reduce the already
accumulated debt to a level that enables macroeconomic stability. Particularly
for Africa, the debt problem has reached an unsustainable level. The
nominal value of Africa’s total debt stock has currently reached $219.3
billion, which is 110% of its GNP and twenty five times its value in
1971. Africa’s debt service ratio is 25% of its total exports up from
9% in 1971. In other words, the debt overhang has to be reduced to free
resources for poverty reduction and also engender debt sustainability. 

In 1996, to
address the issue of the debt burden, the World Bank and the International
Monetary Fund (IMF) launched a program called the Heavily Indebted Poor
Countries (HIPC) initiative to provide debt relief to the poorest and
most indebted countries in the world. Under this initiative, some $12.5
billion worth of debt relief was to be provided to 29 poor countries
including Ethiopia. However, it was soon realized that the relief offered
under this initiative was too little and the process too slow to engender
meaningful debt relief that will contribute towards sustainable development
for the affected countries. Accordingly, in September 1999, these same
institutions enhanced the earlier initiative to provide deeper, faster
and broader debt relief. The enhanced HIPC initiative will more than
double the amount of assistance to over $28.6 billion and increase the
beneficiaries to 32.1  

However, the
mandate of the initiative was broadened quite substantially by requiring
potential beneficiaries not only to pursue sound policies and be committed
to reforms as in the earlier initiative, but to show this commitment
by producing and implementing a thorough program known as Poverty Reduction
Strategy Paper (PRSP). The value of the PRSP goes much beyond the enhanced
HIPC and the resources affected by a successful graduation from this
process (from designing the strategy to achieving the targets established
in the strategy and the monitoring and implementation process in between)
is substantial. It more or less involves the complete aid package that
comes from multilateral and bilateral donors to poor countries. 

Clearly, in
this process, success very much depends on the preparation and implementation
of the PRSP. According to the Bank and the Fund, the PRSP is “a country-owned
action plan, developed through a participatory process, in which poverty-reducing
measures are integrated into a coherent, growth-oriented macroeconomic
framework… Debt relief under the HIPC initiative and access to concessional
lending by the Bank and the Fund is linked to the preparation and implementation
of such poverty reduction strategies.”2  The recipient country prepares
this strategy in a participatory process involving as many of
the stakeholders as possible, including civil society and donors every
step of the way
. The strategy is to be developed in an iterative
process and updated about every 3 years to reflect experience gained
in implementing the strategy. At least in principle, as the IDS Policy
Briefing succinctly summarized, the PRSPs are expected to be:3 

    · Country
    driven. That is, recipient governments will lead the process and there
    would be a broad- based participation in the adoption and monitoring
    of the strategy;

    · It
    must be result oriented or out come based. This requires identifying
    the desired outcomes and instituting a mechanism that lead towards their
    achievement;

    · It
    should be comprehensive in the sense that it takes into account the
    various dimensions of poverty;

    · It
    should be long-term in approach: recognizing the depth and complexity
    of some of the changes needed and

    · It
    should be based on partnership between governments and other actors
    in civil society, the private sector and the donor community. 

Although, as
stated in the above principle, the strategy was to be country owned
and driven, since it has to be finally approved by the Bank and the
Fund, it is at least expected to describe and incorporate, in as much
detail as possible, the following key elements: 

      · The extent, nature, and causes of poverty;

        · Key obstacles to reducing poverty;

          · Long-term poverty reduction goals and
          outcomes;

            · Policies and reforms for achieving
            these goals and their expected costs;

              · The way the strategy is integrated
              into the country’s macroeconomic framework;

                · Identify intermediate indicators that
                will measure progress toward achieving long-term goals;

                  · Indicate the process for involving
                  civil society and others; and

                    · Describe the participatory process
                    for assessing progress. 

                  If we combine
                  the underlying principles and the specific requirements of the PRSP
                  process, we can see that there are opportunities as well as challenges
                  and a number of things can go wrong in the process of formulation and
                  implementation of the whole initiative. To succeed in this process,
                  it obviously requires a conscious, active, substantive and constructive
                  engagement between government and civil society. 

                  The important
                  principle of country ownership of the PRSP process is a significant
                  development in its own right. The value in the concept of ownership
                  is not just symbolic. It has a significant bearing on the likelihood
                  of success of the program. Genuine ownership of programs provides a
                  strong incentive for those involved in implementing it. After all, that
                  is the underlying reason that recommends capitalism as a better form
                  of economic organization for the creation of wealth. Country ownership
                  of the process itself, also adds value by building the capacity of government
                  institutions. If successful, it could build the data collecting and
                  organizing capacity of national statistical offices; it could build
                  monitoring capacity as well as reporting and implementation capacity.  

                  Probably the
                  most valuable opportunity that comes with the PRSP process is its requirement
                  for a genuine participatory process from the design to the implementation
                  and follow-up phases. This is a long overdue recognition among development
                  practitioners and a triumph to civil society institutions (both in the
                  donor and recipient countries) that fought for comprehensive debt relief.
                  It offers an unprecedented opportunity for civil society institutions,
                  particularly those that work very closely in the field of poverty alleviation,
                  to influence anti-poverty policies. Not only that, given the comprehensive
                  nature of the PRSPs, involving not only specific anti-poverty measures
                  but also macroeconomic and expenditure policies of governments, it offers
                  various stakeholders in society to have a say on the country’s overall
                  development policy. This includes academicians, business people, labor
                  unions…etc. who can positively contribute to the policy making process
                  given the chance. Such a broad participatory process has a number of
                  advantages. First, the chances of making egregious mistakes in policy
                  formulation are diminished with wider participation. Secondly, the consensus
                  that such a participatory process engenders is crucial for the success
                  of the policy during implementation as it broadens the ownership base
                  beyond government and its functionaries and reduces policy bickering
                  and reversal mid way through the implementation process thus contributing
                  to policy effectiveness. Finally, such a practice contributes to the
                  overall democratization process in a country. True democratization brings
                  accountability in government and makes the bureaucracy responsive to
                  the concerns of society. In short, building a successful participatory
                  process would improve the overall governance structure of a country
                  with benefits far beyond the resources that come by way of HIPC.
                   

                  However, there
                  are tremendous challenges faced both by recipient countries and donors
                  to make this process work in line with the intention of the initiative.
                  On the part of the recipients, the challenge is to successfully meet
                  the detailed requirements of the initiative particularly as it relates
                  to the preparation and implementation of the process. On the part of
                  donors, the major challenge is to be able to provide the necessary finances,
                  streamline the disbursement process and make the necessary attitudinal
                  change required to make the initiative successful.  

                  Probably the
                  biggest challenge for developing countries is to manage the potential
                  conflict between establishing a genuine participatory process on the
                  one hand and the time constraint on the other. To make the participatory
                  process effective, sufficient time must be allowed for participation
                  or consultation. Information has to flow to potential participants quickly
                  and in a manner that is accessible both in style and language. 
                  Participants must be chosen in a manner that is truly representative
                  of all the stakeholders and there must be a transparent mechanism to
                  follow the process through to its conclusion. Equally important, potential
                  participants must believe the process to be fair and transparent to
                  avoid frustration and cynicism among participants. Furthermore, all
                  this has to be achieved in a time frame that will not cause delay in
                  the preparation and monitoring of the PRSP and this is not going to
                  be easy to achieve. 

                  As mentioned
                  earlier, Ethiopia is one of the presumed beneficiaries from this process.
                  If Ethiopia goes through this process successfully, in addition to the
                  overall benefit to the economy and society that comes from a successful
                  implementation of a good policy, the country could substantially benefit
                  materially by way of debt relief and additional bilateral and multilateral
                  aid over the next few years. Given the substantial resources involved
                  in the initiative and the construction of the program in such a way
                  that it allows, even requires, active participation of civil society
                  in the process, it is important for civil society institutions in the
                  country to prepare for the coming PRSP debates and discussions to make
                  their participation meaningful. Meaningful participation, on the other
                  hand, requires knowledge and information on the issues and processes
                  involved. 

                  In the Ethiopian
                  context, meaningful public participation can only be ensured if civil
                  society members and institutions have a clear idea about the principles
                  behind this initiative, its objectives, the process involved, and the
                  potential problems to be encountered. Since the PRSP, as can be seen
                  in the discussion below, is more or less a broad growth strategy, society
                  must be familiarized with basic principles of economics and determinants
                  of growth. Civil society institutions including institutions working
                  with the poor also need to come up with specific issues and activities
                  that are of concern to their constituencies particularly in relation
                  to policy measures that could be undertaken to reduce poverty. 

                  All this can
                  only be achieved if there is a coherent training program for various
                  civil society institutions including journalists, local NGOs, the business
                  community, labor unions, women’s groups…etc. and the larger public,
                  using various mediums (Radio, Television, News Papers, or organizing
                  public discussion forums.) It is also important to prepare manuals and
                  issue papers on the PRSP in general and on specific policy issues dealing
                  with the process and its implementation in Amharic to help the discussion
                  process. These are activities that the Ethiopian Economic Association,
                  through its recently established research, training and publication
                  wing—the Ethiopian Economic Policy Research Institute—is well suited
                  to undertake.  

                  This proposal
                  is therefore, prepared for funding a number of research, training, publication
                  and eventually advocacy activities over the next few years (January
                  to December 2001 for the preparation of the strategy and the following
                  years for implementation) designed to help make the PRSP process transparent,
                  and encourage and help towards meaningful and effective public participation
                  in the design and implementation of Ethiopia’s full Poverty Reduction
                  Strategy Paper that is due for submission to donors in December 2001. 

                  2.
                   Project Justification
                   

                        2.1.
                  Project Objective
                   

                  Given the above
                  background, the objective of the project is to contribute towards the
                  formulation of good economic policies, good governance and democratization
                  in the country by assisting in the formulation and monitoring of the
                  Poverty Reduction Strategy Paper for Ethiopia through training civil
                  society institutions and preparing manuals and issue papers on various
                  topics related to the PRSP in local languages for the general public.

                        2.1.1.
                  Long-term objectives:
                   

                  Poverty reduction
                  is a very important long-term objective in itself. The project contributes
                  to this long-term objective through its direct contribution to the formulation
                  and implementation of the PRSP. By helping in the active participation
                  of civil society in the process, the project (and of course, the PRSP
                  itself) is also expected to contribute towards good governance and the
                  democratization process in Ethiopia (both important long term objectives
                  for sustainable development) by making policy making transparent and
                  policy implementation subject to informed public scrutiny. 

                        2.1.2.
                  Short-term objective
                   

                  Over the next
                  two to three years, to help make the PRSP process in Ethiopia true to
                  the original design of the process by making PRSP truly country owned,
                  truly participatory, and the final outcome, a true representation of
                  the interest of a broad section of Ethiopian society, particularly the
                  poor. In the implementation phase, to help the public participate in
                  monitoring implementation and ensuring that the priorities agreed in
                  the PRSP are reflected in the government’s annual budget allocations
                  and expenditures. 

                  2.2. The
                  promoter of the project:

                  As suggested
                  in the introduction, the PRSP is essentially an economic strategy with
                  a poverty focus. In terms of profession, while input from various disciplines
                  is important, a bulk of the work lies in the economic profession. The
                  Ethiopian Economic Association is a professional association of economists
                  established in 1991. The main objective of the association is to contribute
                  towards the development of the country’s economy by encouraging research,
                  disseminating the findings of economic research through its various
                  publications, and organizing conferences and round tables to discuss
                  key economic policy issues.

                  In these activities,
                  the association not only has accumulated experiences over the past eight
                  years, but even more, it has proven to be the center of economic policy
                  discussions in the country. Furthermore, the association has recently
                  taken a major step in increasing its capacity to do research, publication
                  and training by establishing a research and advocacy think-tank, the
                  Ethiopian Economic Policy Research Institute (EEA/
                  EEPRI) in order
                  to enable it to do such activities on a continuous and professional
                  basis.

                   

                  Currently,
                  the institute has a fully equipped office space with seven full time
                  research staff (two Ph.D. levels and five M.Sc. levels) with wide experience
                  in their respective fields. (CVs of the full time professional staff
                  is attached as Annex 2 below) It also has a full time data base expert
                  and five full time support staff. Furthermore, the institute can deploy
                  the services of over 700 of the association’s members as the need
                  arises (almost all of them economists with a significant number of experts
                  in a wide range of specialized fields in economics). All this, we believe,
                  qualifies the EEA/EEPRI to undertake this important project successfully. 

                  2.3. Organizational
                  structure and governance
                   

                  As currently
                  envisioned, the project will be managed by a committee within the EEA/EEPRI
                  under the leadership of the director of the institute. A full time project
                  coordinator will be hired to follow the day-to-day activities of the
                  project for at least the first phase of the project and other required
                  personnel out side the institute will be employed on a short-term consultancy
                  basis for specific activities. Financial matters will be handled by
                  the finance department of the institute through a separate account opened
                  for this specific purpose and a separate audited account will be presented
                  to donors on an annual basis until the completion of the project. 

                  2.4. Project
                  Location
                   

                  As can be seen
                  from the list of activities above, the project will be implemented at
                  various locations. However, the center of operation of the project as
                  a whole will be here in Addis at the office of the EEA/EEPRI. Trainings,
                  workshops and public meetings will be held by renting appropriate facilities
                  according to the specific needs of the activity.  

                  3. Outputs
                  and Programming
                   

                  To meet the
                  objectives of the project, at least five interrelated activities will
                  be undertaken. These are: training, workshops, public meetings, media
                  teach-ins and preparation of a set of manuals and issue papers that
                  could be used for training and general public consumption. Specifically,
                  the following activities are envisaged: 

                        3.1.
                  Kinds of activities to be undertaken by the project
                   

                  a. Training 

                    1. Training
                    of about 30-50 local journalists (government and private media) on the
                    PRSP and related issues (one week intensive training)

                    2. Training
                    of trainers of representatives from a number of local NGOs and associations
                    whose work is related to the PRSP (up to 50 people for at least a week)

                    3. Training
                    of a selected number of key parliamentarians from the ruling party and
                    the opposition on economic fundamentals and the PRSP process (about
                    30 members for at least three days)  

                  b.1.
                  Workshops (In the PRSP formulation process)
                   

                    1. Workshop
                    for labor union leaders on the PRSP and identifying labor issues in
                    the PRSP process ( 1-2 days in Addis and in at least two regions)

                    2. Workshop
                    for business leaders and chambers of commerce on the PRSP and identifying
                    the concerns of the business community in the PRSP process (1-2 days
                    in Addis and in at least two other regions)

                    3. A
                    one-day workshop for a larger group of parliamentarians (50-100) to
                    discuss the PRSP process and the role of parliament in the formulation
                    of PRSP

                    4. A
                    workshop for leaders of local NGOs on the PRSP and how to enhance their
                    participation in the preparation of PRSP and incorporate the concerns
                    of their constituency in the PRSP 

                  b.
                  2.  Workshops
                  : (Repeat 1-4 above after adoption of PRSP for
                  monitoring implementation. 

                  c.
                  Public meetings and discussions
                   

                    1.Organize
                    a series of half a day teach-ins in public meetings in all the regions
                    to inform the public about the PRSP process and how to make its voice
                    heard in the process. 

                    2.
                    Organize a series of discussions/debates between civil society institutions
                    and federal and regional government representatives on the PRSP including
                    visions about the strategy, cooperation in the formulation of the strategy
                    and its implementations. 
                     

                  d. Press
                  briefings and media use
                   

                  Using
                  existing media (print and electronic) either free (if available) or
                  through buying advertising space or renting air time, conduct a series
                  of discussions on the media targeted to civil society, on the PRSP,
                  its meaning and potential value including the value of public participation
                  in the process to reach the wider public. 

                  e. Preparing
                  issue papers in Amharic
                   

                  These are important papers that could be used both as teaching materials
                  for the training and eventually for public consumption. In addition
                  to being written in Amharic, these materials shall be written in such
                  a way as to be accessible to a wide audience. They shall also be short
                  and attractive to the reader. We envision at least the following such
                  papers produced: 

                    1. Explaining
                    the PRSP both as a strategy and its application to Ethiopia. It shall
                    contain a brief history of the initiative, its major objectives, the
                    process involved, the amount of money involved in the global package,
                    what Ethiopia expects to gain from the process in terms of designing
                    a good strategy and the material benefit that comes from a successful
                    completion of the package and the value of country ownership and public
                    participation.

                    2. A
                    short paper on poverty: its causes, its effects, poverty indicators,
                    how to fight poverty including the role of the individual, the state,
                    and society in general in this fight against poverty and the process
                    involved in monitoring the effects of a poverty reduction strategy on
                    the poor.

                    3. A
                    similar short paper on principles of macroeconomics and how an economy
                    works both from broad theoretical perspectives and in the Ethiopian
                    context

                    4. A
                    short paper about the budget: how it is prepared, what the various components
                    are, how these components are allocated, the parliamentary process involved
                    in making budget decisions, the sources of finance for the budget, what
                    the budget shows and does not show in relation to total government expenditure,
                    the expenditure process and monitoring budgetary expenditures.

                    5. A
                    short paper on the relationships between good governance, democratization
                    and economic development.

                    6. Other
                    papers depending upon need… 

                  4. Project
                  Duration and training design
                   

                  The totality
                  of the project is expected to take at least three years depending on
                  the time of completion of the full PRSP. The first year will be devoted
                  for activities related to the formulation of the strategy paper. The
                  second and third year activity will be devoted to the process of monitoring
                  the implementation of the completed PRSP. The design of the training
                  and a preliminary outline of the substance of the training are attached
                  as Annex 3 below. 

                  5. Project
                  Budget
                   

                  The total project
                  is estimated to cost 300,808.00 Pound out of this total budget about
                  10.14% or  30,498.00 Pound will be covered from the institute’s
                  own budget while the remaining 89.86% or 270,310 Pound is expected to
                  be raised from various donors interested in the PRSP process in Ethiopia.
                  The budget for the second and third years (phase 2) is very tentative
                  because it is too early to envision the full details of the activities
                  to be undertaken before fully evaluating the activities of the first
                  phase. It is expected that a discussion and budget proposal for the
                  second phase will be presented to donors after a complete evaluation
                  of the project at the end of the first phase. The detailed budget is
                  presented as Annex 1 below.

                   

                  ANNEX
                  I: ESTIMATED BUDGET FOR THE PRSP PROJECT
                  ** 

                  Summary cost estimate in
                  Pound (first phase of the project; First year)

                   
                  No.
                   
                  Activities
                   
                  Labor
                  requirement

                   
                  Cost
                  breakdown detailes
                  Total Cost

                  EEPRI 
                  Share
                  expected
                  from donors
                   
                   
                   
                   
                   
                  Amount
                  In %
                  Amount
                  In %
                  1
                  Develop a project
                  proposal
                  Research Director(RD)
                  & Senior Researchers(SR),EEPRI
                  Cost of 2-weeks
                  part time labor spent on developing the research proposal 

                   
                  1,019.00
                   
                  1019.00
                   
                  100
                   
                  ——–
                   
                  —-
                  2
                  Establish a project
                  coordination capacity

                  – Form
                  a project implementation committee…………………

                  – Place a full-time project
                  coordinator……………………….

                  – Laptop computer for the
                  coordinator……………………….

                  – Printer and photocopy service………………………………

                  – Place a full-time project
                  secretary…………………………..

                  – Project office supplies
                  (paper & stationary)…………………

                  – Prepare and disseminate
                  project brochure………………….

                  – Temporary office rent……………………………………….

                  – Regional facilitators of
                  project implementation…………….

                  – Transport and per-diem allowance
                  for regional facilitators…

                  – Transport
                  allowance for project administration…………….

                   
                   
                  RD
                  and SRs, EEPRI…………

                  One senior professional……..

                  ———–

                  ———–

                  One professional secretary….

                  ———–

                  ———–

                  ———–

                  ———– 

                  ———–

                  ———–

                   
                   
                  Part
                  time labor cost spent by EEPRI staff……

                  Full-time one-year salary of
                  the coordinator….

                  Laptop computer for the coordinator…………

                  Use of EEPRI’s printer &
                  photocopy facilities.

                  Full-time one-year salary of
                  the secretary……

                  Auxiliary office equipment
                  and supplies…….

                  Printing cost of a brochure
                  about the project..

                  Two room office rent for one
                  year……………

                  0ne-month salary for 11 coordinators………..

                  500 USD per regional activities………………

                  Fuel cost and car rental……………………….

                   
                   
                  6,793.00

                  8,151.00

                  2,377.00

                  2,038.00

                  1,189.00

                  5,434.00

                  1,359.00

                  3,396.00

                  3,736.00

                  3,736.00

                  6,793.00

                   
                   
                  6,793.00

                  ——–

                  ——–

                  ——–

                  ——–

                  ——–

                  ——–

                  ——–

                  ——–

                  ——–

                  ——– 

                   
                   
                  100

                   
                   
                  ———

                  8,151.00

                  2,377.00

                  2,038.00

                  1,189.00

                  5,434.00

                  1,359.00

                  3,396.00

                  3,736.00

                  3,736.00

                  6,793.00

                   
                   

                  100

                  100

                  100

                  100

                  100

                  100

                  100

                  100

                  100

                  100

                  3
                  Commission the
                  preparation of manuals on PRSP and related matters


                  Five Manuals  described in the project doc……………… ..

                  – Translation into Amharic(national
                  lang.)……………………

                  – Publish manuals (2000 copies
                  each) in hard cover…….……

                   

                  Five
                  experts & RD, SR,EEPRI..

                  Five professional translators…..

                  ————

                   
                   
                  2038
                  pound/manual and part-time labor…

                  679 pound/manual……………………….

                  4075 pound/manual for five 
                  manuals……

                   
                   
                  12,227.00

                    3,396.00

                  20,378.00

                   
                   
                  2,038.00

                  ————

                  ————

                   

                  17
                   
                   
                  10,189.00

                  3,396.00

                  20,378.00

                   
                   
                  83

                  100

                  100

                  4
                  Provide training
                  on PRSP

                  I. Training programs

                  a) Training of about 30-50 journalists………………………..

                  b) Training
                  of about 30-50 key parliamentarians…………….

                  c) Training
                  of up to 50 trainers from NGO representatives….

                  d) Training
                  program(2) for about 30 regional representatives..  

                  II. Training
                  support facilities

                  a) Training
                  hall facilities rental (6 days * 5)………………….

                  b)Duplicating
                  & binding training materials(issue papers,etc).

                  c) Meal &
                  refreshment during training ………………………

                  d) Transport,
                  hotel & per-diem for participants from regions..

                   
                   
                  Eight
                  resource persons & RD.

                  Eight resource persons &
                  RD.

                  Nine resource persons &
                  RD..

                  Nine resource persons &
                  RD.. 
                   

                  ————-

                  ————-

                  ————-

                  ————-

                   
                   
                  679
                  pound/issue paper and first lecture………

                  136 pound/additional lecture………………….

                  136 pound /additional lecture…………………

                  136 pound /additional lecture………………… 
                   

                  679 pound/training program….………………

                  6.79 pound/ paper (6.79*40*5*8
                  papers)……

                  6.79 pound/day/participant
                  (6.79*200*6)……

                  169.8 pound/participant (60*169.8)…….……

                   
                   
                  5,774.00

                  1,426.00

                  1,562.00

                  3,125.00 
                   

                  3,396.00

                  10,868.00

                  8,151.00

                  10,189.00

                   
                   
                  1,019.00

                  340.00

                  475.00

                  951.00 
                   

                  ———

                  ———

                  ———

                  ———

                   
                   
                  18

                  24

                  30

                  30

                   
                   
                  4,755.00

                  1,086.00

                  1,087.00

                  2,174.00 
                   

                  3,396.00

                  10,868.00

                  8,151.00

                  10,189.00

                   
                   
                  82

                  76

                  70

                  70 
                   

                  100

                  100

                  100

                  100

                  5
                  Undertake workshops
                  and public meetings

                  – Organize a workshop for
                  labor union leaders……

                  – Organize a workshop for
                  parliamentarians………

                  – Organize a workshop for
                  NGOs and associations.

                  – Organize a workshop for
                  business representatives

                  – Undertake a public meeting(debate)
                  between       represent. of civil societies
                  & federal government…

                  – Undertake public meetings(debates)in
                  each region

                  –  Hall rental and refreshments…………………….

                   
                  RD,
                  SR & three experts….

                  RD, SR & three experts….

                  RD, SR & three experts….

                  RD, SR & three experts….  

                  4 C.S. & 2 gov. represen…

                  4 C.S. & 2 gov. represen…

                  ————

                   
                  271.7
                  pound/expert & EEPRI staff contri. .

                  271.7 pound /expert & EEPRI
                  staff contri.

                  271.7 pound /expert & EEPRI
                  staff contr..

                  271.7 pound /expert & EEPRI
                  staff contri.. 

                  271.7 pound/representative
                  & EEPRI staff..

                  136 pound/representative &
                  EEPRI staff..

                  1019 pound/meeting for a total
                  of 16……

                   
                  1,223.00

                  1,223.00

                  1,223.00

                  1,223.00 
                   

                  2,038.00

                  13,449.00

                  16,302.00

                   
                  408.00

                  408.00

                  408.00

                  408.00 
                   

                  408.00

                  4,483.00

                  ——-

                   
                  33

                  33

                  33

                  33 
                   

                  20

                  33 

                   
                  815.00

                  815.00

                  815.00

                  815.00 
                   

                  1,630.00

                  8,966.00

                  16,302.00

                   
                  67

                  67

                  67

                  67 
                   

                  80

                  67

                  100

                  6
                  Conduct discussions
                  and teach-ins in the media

                    i)Broadcast key PRSP
                  issues in FM radio

                           – Prepare 12 ten-minute messages………….

                           
                  – Negotiate suitable air-time………………..

                  ii) Discuss key PRSP elements
                  on TV

                           – Undertake 12 ten-minute discussions……

                           
                  – Negotiate suitable air-time………………..

                  iii)
                  Publish key articles on PRSP in news papers

                          
                  – Prepare 12 articles on PRSP………………

                         
                  – Negotiate column space
                  in news papers

                   
                   
                  Six
                  program writers……….

                  ———– 

                  Six program presenters……

                  ———–   

                  12 articles writers…………

                  ————-

                   
                   

                  204 pound/ 20 min. program each …

                  10min./week for a total of
                  12 weeks………

                  408.00 pound/ 20 min. program
                  each ……

                  10min./week for a total of
                  12 weeks………  

                  135.85 pound/article …….……………….

                  Full page/article on 12 news
                  papers……….

                   
                   
                  1,223.00

                  4,755.00

                        
                  2,445.00

                  3,396.00 

                  1,630.00

                  2,038.00

                   
                   
                  ——–

                  ——–

                  ——–

                  ——– 

                  ——–

                  ——–

                   
                   
                   
                  1,223.00

                  4,755.00

                  2,445.00

                  3,396.00 

                  1,630.00

                  2,038.00

                   
                   
                  100

                  100

                  100

                  100 

                  100

                  100

                   
                  Total cost
                   
                   
                  178,678.00
                  19,154.00
                  11
                  159,524.00
                  89

                   

                  Summary cost estimate in
                  Pound (second phase of the project: 2
                  nd and
                  3
                  rd year)

                   
                  No.
                   
                  Activities
                   
                  Labor
                  requirement

                   
                  Cost
                  breakdown detailes
                  Total Cost

                  EEPRI 
                  Share
                  expected
                  from donors
                   
                   
                   
                   
                   
                  Amount
                  In %
                  Amount
                  In %
                  1
                  Translate, duplicate
                  & disseminate PRSP document

                  – Translate PRSP into national
                  language………….

                  – Produce
                  5000 copies of  PRSP…………………………….

                  – Distribute copies at federal
                  and regional levels…………….

                   
                   
                  Two
                  professional translators…

                  ———–

                  ———–

                   
                   
                  13.59/page
                  (10*100)……………………….

                  6.793/document…………………………….

                  0.679/document………………………………

                   
                   
                  1,359.00

                  33,963.00

                  3,396.00

                   
                   
                  ——–

                  ——–

                  ——–

                   

                   

                  1,359.00

                  33,963.00

                  3,396.00

                   
                   
                  100

                  100

                  100

                  2
                  Produce expert
                  opinions on the PRSP’s sectoral, inter sectoral and overall development
                  implications

                  – Organize round-table discussions
                  on the PRSP implement..

                  – Publish discussion papers
                  in FOCUS……………………

                   

                  15
                  experts & RD, SR,EEPRI..

                  EEA editor

                   
                   
                  340
                  pound/expert and EEPRI staff……..…..

                  EEA editor contribution…..……………….

                   
                   
                  6,792.00

                    1,019.00

                   
                   
                  1,698.00

                  1,019.00

                   
                   
                  25

                  100

                   
                   

                  5,094.00

                  ——-

                   
                   
                  75 

                  3
                  Provide training
                  on monitoring and evaluation of the PRSP implementation

                  I. Training programs

                  a) Training of about 30-50 journalists………………………..

                  b) Training
                  of about 30-50 key parliamentarians…………….

                  c) Training
                  of up to 50 trainers from NGO representatives….

                  d) Training
                  program(2) for about 30 regional representatives..  

                  II. Training
                  support facilities

                  a) Training
                  hall facilities rental (6 days * 5)………………….

                  b) Duplicating
                  and binding background (issue) papers………

                  c) Meal &
                  refreshment during training ………………………

                  d) Transport
                  & per-diem for participants from regions………

                   

                  Eight
                  resource persons & RD.

                  Eight resource persons &
                  RD.

                  Nine resource persons &
                  RD..

                  Nine resource persons &
                  RD.. 
                   

                  ————-

                  ————-

                  ————-

                  ————-

                   

                  679/issue
                  paper and first lecture………

                  136/additional lecture…………………..

                  136/additional lecture…………………..

                  136/additional lecture………………….. 
                   

                  136/training program……………………

                  3.4/ paper (5*40*8 papers)………………..

                  3.4/day/participant (3.4*200*6)…………….

                  101.9/participant (60*101.9)……………….

                   

                  5,774.00

                  1,426.00

                  1,562.00

                  1,124.00 
                   

                  679.00

                  679.00

                  4,075.00

                  6,113.00

                   

                  340.00

                  340.00

                  475.00

                  950.00 
                   

                  ———

                  ———

                  ———

                  ———

                   

                  6

                  24

                  30

                  30

                   

                  5,434.00

                  1,086.00

                  1,087.00

                  2,174.00 
                   

                  679.00

                  679.00

                  4,075.00

                  6,113.00

                   

                  94

                  76

                  70

                  70 
                   

                  100

                  100

                  100

                  100

                  4
                  Undertake workshops
                  and public meetings on progress made in the PRSP implementation

                  – Organize a workshop with
                  labor union leaders…

                  – Organize a workshop with
                  parliamentarians……

                  – Organize a workshop with
                  NGOs and associations

                  – Organize a workshop with
                  business representative

                  – Undertake a public meeting 
                  between       represent. of civil societies
                  & federal government…

                  – Undertake public meetings
                  in each region

                  –  Hall rental and refreshments…………………….

                   
                   
                  RD,
                  SR & three experts….

                  RD, SR & three experts….

                  RD, SR & three experts….

                  RD, SR & three experts….  

                  4 C.S. & 2 gov. represen…

                  4 C.S. & 2 gov. represen…

                  ————

                   
                   
                  271.7/expert
                  & EEPRI staff contri. ……

                  271.7/expert & EEPRI staff
                  contri. ……

                  271.7/expert & EEPRI staff
                  contri……

                  271.7/expert & EEPRI staff
                  contri. …… 

                  271.7/representative &
                  EEPRI staff……

                  136/representative & EEPRI
                  staff……

                  1015.6/meeting for a total
                  of 16……….

                   
                   
                  1,223.00

                  1,223.00

                  1,223.00

                  1,223.00 
                   

                  2,038.00

                  13,449.00

                  16,302.00

                   
                   
                  408.00

                  408.00

                  408.00

                  408.00 
                   

                  408.00

                  4,483.00

                  ——-

                   
                   
                  33

                  33

                  33

                  33 
                   

                  20

                  33 

                   
                   
                  815.00

                  815.00

                  815.00

                  815.00 

                  1,630.00

                  8,966.00

                  16,302.00

                   
                   
                   
                  67

                  67

                  67

                  67 
                   

                  80

                  67

                  100

                  5
                  Conduct PRSP implementation
                  assessment in the media

                    i)Broadcast key PRSP
                  issues in FM radio

                           – Prepare 12 ten-minute messages………….

                           
                  – Negotiate suitable air-time………………..

                  ii) Discuss key PRSP elements
                  on TV

                           – Undertake 12 ten-minute discussions……

                           
                  – Negotiate suitable air-time………………..

                  iii)
                  Publish key articles on PRSP in news papers

                          
                  – Prepare 12 articles on PRSP………………

                         
                  – Negotiate column space
                  in news papers

                   

                  Six
                  program writers……….

                  ———– 

                  Six program presenters……

                  ———–   

                  12 articles writers…………

                  ————-

                   

                  211/
                  20 min. program each …………

                  10min./week for a total of
                  12 weeks………

                  422/ 20 min. program each …………

                  10min./week for a total of
                  12 weeks………  

                  136/article …………………………..

                  Full page/article on 12 news
                  papers……….

                   

                  1,223.00

                  4,755.00

                        
                  2,445.00

                  3,396.00 

                  1,630.00

                  2,038.00

                   

                  ——–

                  ——–

                  ——–

                  ——– 

                  ——–

                  ——–

                   
                   

                  1,223.00

                  4,755.00

                  2,445.00

                  3,396.00 

                  1,630.00

                  2,038.00

                   

                  100

                  100

                  100

                  100 

                  100

                  100

                   
                  Total cost
                   
                   
                  122,130.00
                  11,344.00
                  9
                  110,786.0
                  91
                   
                  Overall project
                  cost
                   
                   
                  300,808.00
                  30,498.00
                  10
                  270,310.0
                  90

                   

                  Annex II. Summery
                  of EEA/EEPRI Research and Support staff
                   
                   

                  No.
                  Name
                  Institutional
                  Title

                  Education
                  and Field

                  Experience

                  I.  Full time Research
                  Staff

                  1.
                  Berhanu
                  Nega
                  Director
                  Ph.D.
                  , Economics, the New School for Social Research U.S.A
                  11
                  years  Teaching and Research
                  2.
                  Getachew
                  Asgedom
                  Senior
                  Researcher (Agriculture and Related areas)
                  Ph.D.,
                  in Econometrics University of New England Armidale, Australia
                  12
                  years

                  Teaching and Research

                  3.
                  Getahun
                  Tafesse
                  Senior
                  Researcher (Poverty and Human Resource)
                  M.Sc.
                  Degree in Social Policy and Planning in Developing Countries

                  London School of Economics,
                  London University, U.K

                  14
                  years as an Expert and Senior Expert in Policy planning and implementation
                  4.
                  Daniel
                  Assefa
                  Assistant
                  Researcher (Poverty and Human Resource

                  M.Sc.,
                  Human Resource Economics

                  Addis Ababa University

                  5
                  years as an expert, Training Secretary and Project coordinator
                  5.
                  Elias
                  Kedir
                  Assistant
                  Researcher (Trade and Industry)

                  M.Sc.
                  in Economic Policy Analysis

                  Addis Ababa University

                  5
                  years as an analyst and Lecturer
                  6.
                  Paulos
                  Gutema
                  Assistant
                  Researcher (Agriculture and Related Areas)
                  M.Sc.
                  in Economic Policy , Addis Ababa University
                  15
                  years
                  7.
                  Daniel
                  Aklilu
                  Database
                  System Expert
                  B.Sc.
                  in Statistics, Addis Ababa University
                  4
                  years as Computer Trainer and Programmer
                  Under
                  Recruitment

                  8.

                  Senior
                  Researcher (Trade and Industry)


                  No.
                  Name
                  Institutional
                  Title

                  Education
                  and Field

                  Experience

                  II.  Full time Administrative 
                  Professional Staff

                  1.
                  Abera Bejiga
                  Head,
                  Administration and Finance
                  B.Sc.
                  in Accounting from Addis Ababa University
                  20
                  years as Administration and Finance Head
                  2.
                  Rahel Yilma
                  Publication
                  Assistant
                  M.
                  Sc. in Petroleum Economics
                  13
                  years in Different positions
                  3.
                  Bruktawit Mengesha
                  Executive
                  Secretary/Administrator
                  Diploma
                  in Secretarial Science and Office management
                  5
                  years as a Secretary
                  III. 
                  Full time Administrative Non-professional staff

                  1.
                  Metasebia Zelalem
                  Membership
                  Administrator
                  12 
                  complete and Computer Diploma
                  1
                  year and 9 months
                  2.
                  Hiwot Kassa
                  Affairs
                  Executioner
                  12
                  complete and Computer Diploma
                  5
                  years in the field
                  IV. 
                  Full time Administrative Professional Supporting Staff Under Recruitment

                  1.

                  Librarian


                  2.

                  Assistant
                  Secretary

                   
                   

                  * Curriculum Vitae are available
                  upon request. 

                   

                  ANNEX III:
                  MANUALS, TRAINING DESIGN AND COURSE OUTLINE

                   

                  I. Manuals
                  and Issue Papers
                   

                  The following
                  manuals will be prepared for wide distribution in English and Amharic. 

                  1. Manual
                    on the Concepts and Measurement of Poverty, Inequality, Risk and Vulnerability

                   

                    The concept
                    of poverty in the context of the trend in development thinking

                    The definitions
                    of poverty, inequality, risk and vulnerability

                    The methodologies
                    of poverty measurement and assessment of risk & vulnerability

                    Characteristics
                    of poverty and its causes

                    The social
                    and economic effects of poverty, inequality, risk and vulnerability

                    Indicators
                    of poverty, inequality, risk and vulnerability 

                  1. Manual
                    on the Concepts of Democracy and Development

                   

                    Is democratization
                    necessary for economic development?

                    The process
                    of democratization

                    Good governance

                    Peoples’
                    participation

                    Indicators
                    of democracy and good governance

                    Development
                    as freedom 

                  1. Manual
                    on the Poverty Reduction Strategy Paper (PRSP)

                   

                              Background on the history and concept
                  of PRSP

                              A note on International Development
                  Targets

                        How
                  to undertake a diagnostic review of the poverty situation

                    The relationship
                    between public policy and poverty reduction (the transmission mechanism:
                    Macro ®
                    Meso ®Micro)

                    Elements
                    of a strategy

                    PRSP as
                    a growth strategy (PRSP, Macroeconomic fundamentals and economic growth)

                        Monitoring
                  and evaluating the strategy 

                  1. Manual
                    on the public budget, expenditure and monitoring processes

                   

                    Budgets,
                    Budget deficits, and their relationship with macroeconomic stability

                    How public
                    revenue is generated

                    The budget
                    preparation process and its components

                    The process
                    of identifying priority sectors and expenditure items

                    Public
                    expenditure monitoring and evaluation system  

                  1. Manual
                    on the Ethiopian economy

                   

                        The
                  structure of the Ethiopian economy

                        Economic
                  agents and their role in the economy

                        Planning
                  and policy formulation processes

                        The
                  state of socio-economic development and its indicators

                        Inter
                  linkages and relationships among various economic variables

                        The
                  root causes of underdevelopment

                        The
                  development resource potential of the country

                        Elements
                  of a stable macroeconomic environment 

                  II. Training
                  Design
                   
                   

                   
                  Training format
                   

                  Two types of
                  training will be conducted. One targeting beneficiaries directly and
                  the other indirectly through training of trainers.  In direct training
                  of beneficiaries, the focus will be on specific contents and issues
                  while in training of trainers a general approach to processes of understanding
                  contents and identifying issues will be the main focus of the training. 
                  The trainers will also be trained in the design, objectives and implementation
                  processes of this project and encouraged to adopt the overall approach
                  to their respective constituencies.  

                  Training will
                  be provided in the form of tutorial lecture supported by a variety of
                  training instruments rather than one-way teaching.  Extreme care
                  will be taken in identifying resource persons that have not only thorough
                  knowledge of concepts and issues but also a good understanding of the
                  Ethiopian economy and ability to use and apply the Ethiopian context.
                  Trainees will be provided with necessary materials (issue papers and
                  manuals) in advance of the training and encouraged to make the necessary
                  preparation for active participation during the training. Participants
                  will be encouraged to ask questions and debate on issues, while guided
                  by the resource person to reach on consensuses that accommodate and
                  respect different opinions. Trainers will be experienced teachers at
                  a university level. 

                  In the preparation
                  of the training materials, maximum effort will be made to explain subjects
                  in the context of Ethiopia. The materials will be prepared in easily
                  understandable phrases and short statements that avoid abstract and
                  jargon words.  Similarly, the resource persons are encouraged to
                  use local examples in making and illustrating points. Lectures, in as
                  much as possible, will be accompanied by visual displays of charts and
                  diagrams including video shows.  Whenever convenient, group discussions
                  and exercises will be used to complement lectures.  

                  Preliminary
                  Course Design
                   

                  Each training
                  program will have the following core subjects of study for which a short
                  issue paper will be prepared: –

                     Day
                  1:  Basic Macroeconomics and the Ethiopian Economy

                   

                    a) How does
                    an economy work? What are the key assumptions about the behavior of
                    economic agents?

                    b) Basic
                    Principles of macroeconomics

                    c) The role
                    of government in the economy

                    d) Determinants
                    of economic growth in developing countries

                    Day
                    2: The Ethiopian Economy

                   

                    a) The structure
                    of the Ethiopian Economy

                    b) Economic
                    performance over the past four decades

                    c) Organization
                    of the economy under the Imperial, Derge and current regimes and their
                    underlying philosophies

                    d) Globalization
                    and its effect on the Ethiopian economy

                    Day
                    3: Poverty in Ethiopia

                   

                    a) Concepts
                    of poverty and its measurements

                    b) The dynamics
                    and characteristics of poverty in Ethiopia

                    c) Inequality,
                    risk and vulnerability in Ethiopia

                    d) Policy
                    instruments for poverty reduction

                    e) Poverty
                    reduction measures and the requirements of macroeconomic stability (conflicts
                    and complementarities)

                    Day
                    4: The Poverty Reduction Strategy Paper

                   

                    a) International
                    Development Targets

                    b) PRSP
                    and the enhanced HIPC; History, underlying philosophy and basic concepts

                    c) Ethiopia’s
                    potential benefit from the initiative

                    d) The PRSP
                    process and the value of public participation 

                    Day
                    5: Formulating a Strategy and including the concerns of specific constituencies
                    in the strategy
                     

                    a) What
                    the final PRSP would look like

                    b) Approaches
                    to formulating the strategy

                    c) Identifying
                    areas in the strategy for inclusion to reflect interests of specific
                    constituencies

                    Day
                    6: Strategies for effective public participation

                   

                    a) Public
                    participation, Democracy and economic development

                    b) Good
                    governance and economic development

                    c) Strategies
                    for effective public participation

                  Issue Papers
                  to be Prepared

                   

                        1. 
                  PRSP background, objectives, content and processes

                        2.
                  Concepts of poverty and its measurement methodologies

                        3.
                  Inequalities, Risk and Vulnerability

                        4.
                  Good governance, democracy and development

                        5.
                  The principles of basic economics

                        6.
                  Basic structures of the Ethiopian economy

                        7.
                  The dynamics and characteristics of poverty in Ethiopia

                        8.
                  Steps and approaches in formulating a strategy 

                  Implementation
                  procedures
                   

                  The implementation
                  committee
                  of the project needs to be established up on the approval
                  of the project by donors.  The committee is expected to hold regular
                  meetings, at least once a week following the commencement of the project
                  implementation.  The committee will decide on all major aspects
                  of the project implementation including the selection and hiring of
                  a project coordinator and training resource persons, work plan and budget
                  revisions and update.   

                  Placement of
                  additional project staff will follow the institute’s regular procedure
                  of hiring temporary staff.  Job positions will be advertised in
                  advance and applications reviewed and short-listed before interview
                  and selection.  The institute’s interview rating format will
                  be used to rank short-listed applicants.   

                  In as much
                  as possible training materials need to be prepared by the resource persons
                  who will be providing the training. The training materials need to be
                  reviewed and approved by the project implementation committee. 
                  The committee will identify relevant beneficiaries and also decide on
                  the size and composition of trainees for a given training.  The
                  committee may also decide to provide training on demand, subject to
                  considerations of relevance and appropriateness. 

                  Potential beneficiaries
                  and participants of project activities will be approached directly and
                  through formal letters.  This should be followed by detailed discussions
                  with the representatives of the beneficiaries to accommodate their needs
                  in the training design and finalize the details of the training including
                  duration, place, format and so on. 

                  Mid-project
                  implementation, a workshop will be organized to discuss progress in
                  implementation, achievement and constraints with concerned individuals,
                  representatives of project beneficiaries and donors.   Monitoring
                  and evaluation instruments incorporated in the project design will be
                  used to prepare progress reports and evaluate the status of the project. 
                  Quarterly progress reports will also be submitted to donors with whom
                  the committee will undertake bi-annual meetings. 

                  ANNEX III:
                  PROJECT IMPLEMENTATION MONITORING
                  SYSTEM

                   

                  No.
                  ACTIVITIES
                  MONITORING SYSTEM
                  INDICATORS
                  1
                  Overall project administration
                  & supervision
                  A committee comprising the
                  Director, Senior Researcher and Administrative Officer of the Institute
                  will be established
                  Minutes of monthly meetings
                  of the committee
                  2
                  Establishing a project coordination
                  capacity
                  A project coordination office
                  will be established
                  Recruitment of a project coordinator
                  and renting of an office
                  3
                  Preparation of manuals
                  Contract evaluation and review
                  of draft manuals by senior staff of the Institute and conducting workshops
                  on final draft manuals
                   
                  4
                  Training on the PRSP
                  Identification of appropriate
                  trainers who have the requisite experience and qualification 

                  Training evaluation
                  questionnaire will be developed and implemented

                  The mixture of trainees 

                  Feed back questionnaires
                  filled by trainees

                  5
                  Monitoring project implementation
                  progress
                  Regular(quarterly) reports
                  prepared for the project financer by the project coordinating committee 

                  Organization
                  of a mid-term project evaluation workshop

                   

                   

                      

                  *
                  A preliminary draft. 

                  1
                  In 1996, the Bank and the Fund classified 41countries as heavily indebted
                  poor countries. This included, for analytical purposes 32 countries
                  with a 1993 GNP per capita of $695 or less and 1993 present value of
                  debt to exports higher than 220 per cent or present value of debt to
                  GNP higher than 80 percent. Also included were nine countries that received,
                  or were eligible for, concessional debt rescheduling from bilateral
                  creditors. In 1998, Nigeria no longer met the criteria, and Malawi was
                  added. In 1999 the number of countries was reduced to 40 because Equatorial
                  Guinea no longer met the criteria for “low income” or “heavily
                  indebted.” By September 2000, the number has gone back to forty-one.
                  Thirty-three of the forty-one countries are in Africa while thirty-two
                  are in sub-Saharan Africa. See IMF “ Debt Initiative for the Heavily
                  Indebted Poor Countries (HIPCs): A fact sheet, September, 2000. See
                  also United States General Accounting Office, “Developing Countries:
                  Debt Relief Initiative for Poor Countries Faces Challenges.” GAO/NSIAD-00-161,
                  June 2000, p.8 and note 6, p. 11.

                  2
                  The World Bank Group and The International Monetary Fund, Memorandum
                  to Members of the International Monetary and Financial Committee and
                  Members of the Development Committee on “Progress Reports on Heavily
                  Indebted Poor Countries (HIPC) and Poverty Reduction Strategy Papers
                  (PRSPs)”, April 15, 2000, p.1.

                  3
                  Institute of Development Studies, Policy Briefing, Issue 13, April 2000,
                  p.1.

                  ** The second phase budget is highly
                  tentative and should be taken as a rough indicator. The activities to
                  be undertaken in the implementation phase shall be informed by the experiences
                  of the first phase of the project. It is for example assumed that the
                  project will not need a full time staff and an office after the first
                  year. But, this could change after evaluation of the first year experience.
                  A more precise budget will be prepared and negotiated with donors once
                  the first phase is completed and evaluated.